Occupied hostel case study
Passive fire protection at Booth House, Whitechapel
A £500,000+ passive fire protection programme delivered over six months in controlled phases throughout an occupied Whitechapel hostel housing more than 200 residents. FireX coordinated intrusive surveying, fire stopping, fire damper servicing, rated ceilings, access panels and fire door works while maintaining safe occupation.

Project requirement
The challenge.
Following an extensive compartmentation survey, NACCS consulted a number of passive fire protection contractors about the remedial programme at Booth House. FireX was appointed on the strength of its proposed methodology, level of detail and phased delivery strategy. The hostel remained occupied by more than 200 residents throughout the works, so every phase had to maintain safe access, protect residents and staff, and preserve the building’s continued operation while extensive opening-up and remedial works progressed.
Delivery control
How the work was managed.
FireX developed a construction phase plan and delivered the project over six months from June 2025, working in controlled phases from the basement through six storeys and the plant room. The programme included an intrusive compartmentation survey, the removal of non-compliant fire-stopping foam and the installation of complete FSi fire-stopping systems to the project fire strategy. FireX also inspected and serviced 92 fire dampers, replacing fused links where required; removed and replaced more than 1,000 m² of ceilings with 60-minute fire-rated systems; installed more than 250 fire-rated access panels; installed over 40 FD30S doorsets; and repaired and maintained 52 existing fire doors. Electrical and fire-alarm subcontractors were managed alongside the passive fire works, with building management, security and other stakeholders involved throughout.
Scope of works
Scope delivered.
A six-month, multi-service programme covering more than 2,500 penetrations, 92 fire dampers, over 1,000 m² of rated ceilings and extensive fire door works in an occupied building.
- Intrusive fire compartmentation survey
- Removal of non-compliant fire-stopping foam
- FSi fire-stopping systems to 2,500+ penetrations
- Inspection and servicing of 92 fire dampers
- Replacement of fused links where required
- Removal and replacement of 1,000+ m² of 60-minute fire-rated ceilings
- Installation of 250+ 60-minute fire-rated access panels
- Installation of 40+ FD30S doorsets
- Repairs and maintenance to 52 existing fire doors
- Electrical and fire-alarm subcontractor management
- Protection, cleaning and decorative making-good
Completion evidence
Traceable records for the completed works.
FireX prepared installation and inspection records using its BM TRADA Q-Mark recording process where applicable, together with the other project-specific records required for review and practical close-out.
- Construction phase plan
- Phased work-area and occupation controls
- Location-linked fire-stopping installation records
- Fire damper inspection and service records
- Fire door survey, installation and maintenance records
- Completion records for fire-rated ceilings and access panels
Related capability
Services used on comparable requirements.
Every scope is confirmed against the building, available evidence and the limits of the relevant certification.
View residential buildings capabilityProgramme outcome
Complex remedial works delivered while the hostel remained occupied.
The £500,000+ programme brought together compartmentation, fire stopping, fire dampers, rated ceilings, access panels and fire door works within one coordinated delivery strategy. Careful phasing, work-area protection, cleaning and stakeholder liaison allowed the hostel to remain operational for more than 200 residents throughout the six-month programme.
Explore FireX fire stoppingTalk to FireX
Planning a similar programme?
Share the building type, location, asset quantities, available survey information and target programme. We’ll review the requirement and set out the practical next step.