Healthcare case study

Fire stopping at SEON Vision Kingston Eye Clinic

A £15,000+ fire-stopping remedial programme completed within one week at SEON Vision’s new Kingston eye clinic. FireX treated and recorded 41 service penetrations at the compartment line separating the ground-floor commercial unit from the residential accommodation above.

41penetrations treatedNamed FireX project
Reception at SEON Vision’s completed Kingston upon Thames eye clinic
SEON Vision · 140 London Road, Kingston upon Thames, KT2 6QL
ClientSEON Vision
Location140 London Road, Kingston upon Thames, KT2 6QL
BuildingMixed-use building with residential accommodation above
FireX work areasGround-floor commercial unit
SectorHealthcare
Project dateJuly 2024
DurationOne week
Project value£15,000+
DeliverySurvey-led, out-of-hours works
Recorded quantities41 service penetrations

Project requirement

The challenge.

After construction of the new eye clinic had begun, a fire risk assessment commissioned by the freeholder identified missing and damaged compartmentation between the ground-floor commercial unit and the residential accommodation above. SEON Vision was working to a strict construction programme and assisted the freeholder in progressing the required remedial works. FireX was contacted to assess the affected areas, define the necessary fire-stopping scope and complete the work without delaying the wider clinic fit-out.

Delivery control

How the work was managed.

FireX attended promptly, surveyed the affected areas and provided a defined quotation. The remedial works were completed over a one-week period and undertaken out of hours to minimise disruption to the construction programme. FSi products were installed within suitable tested fire-stopping systems to address the identified defects at the compartment line between the new ground-floor eye clinic and the residential units above.

Scope of works

Scope delivered.

All 41 identified service penetrations were treated and recorded within a one-week, out-of-hours programme that helped the clinic fit-out remain on schedule.

  • Fire stopping to 41 service penetrations
  • Service penetration sealing
  • Linear gap and joint seals
  • Intumescent pipe collars and wraps

Completion evidence

Traceable records for the completed works.

FireX prepared installation and inspection records using its BM TRADA Q-Mark recording process where applicable, together with the other project-specific records required for review and practical close-out.

  • Penetration location and reference
  • Dimensions of the penetration
  • Products and systems used
  • Specified fire-resistance rating
  • Before-and-after photographs
  • Additional installation and traceability information required by the project and FireX’s certified process

Related capability

Services used on comparable requirements.

Every scope is confirmed against the building, available evidence and the limits of the relevant certification.

View healthcare capability

Programme outcome

Forty-one penetrations completed within one week.

All 41 identified service penetrations were treated and recorded within the one-week programme. Completing the work out of hours helped the clinic fit-out remain on schedule while addressing the FRA-identified defects in the compartmentation separating the ground-floor commercial unit from the residential accommodation above.