Public building case study

Passive fire protection at Camden Town Hall

A £250,000+ passive fire protection programme delivered over five months during the refurbishment of Camden Town Hall, comprising fire stopping to approximately 510 service penetrations, FIREFLY fire barriers and the installation of 38 mechanical fire dampers.

510penetrations treatedNamed FireX project
Camden Town Hall stone façade and entrance lettering on Judd Street
MG Construction · 5 Judd Street, London, WC1H 9JE
ClientMG Construction
Location5 Judd Street, London, WC1H 9JE
BuildingHistoric five-floor civic building
FireX work areasBasement to third floor
SectorPublic building
Project dateFebruary 2026
DurationFive months
Project value£250,000+
DeliveryPhased refurbishment
Recorded quantitiesApprox. 510 penetrations · 38 dampers

Project requirement

The challenge.

MG Construction, the principal contractor and fit-out specialist, appointed FireX to deliver the project’s passive fire protection elements during the refurbishment of Camden Town Hall. FireX’s works extended from the basement through to the third floor, covering office accommodation, civic facilities and public event spaces. The project was operating to a strict construction programme, so each phase needed to be completed and recorded in coordination with MG Construction and the wider project team, allowing areas to progress to follow-on trades without avoidable delay.

Delivery control

How the work was managed.

FireX delivered the works through a five-month phased programme commencing in February 2026. Activities were coordinated with the refurbishment sequence and the availability of individual work areas. Approximately 510 service penetrations were treated using FSi fire-stopping products within suitable tested systems. The wider scope included linear gap and joint sealing, intumescent pipe collars and wraps, FIREFLY fire barrier systems and the installation of 38 mechanical fire dampers. Installations were completed in accordance with the project fire strategy, relevant tested system evidence, manufacturer requirements and the applicable limits of FireX’s certification.

Scope of works

Scope delivered.

Approximately 510 service penetrations completed and 38 mechanical fire dampers installed across the basement to third floor during a five-month phased programme.

  • Service penetration sealing
  • Linear gap and joint seals
  • Intumescent pipe collars and wraps
  • FIREFLY fire barrier system
  • Mechanical fire damper installation

Completion evidence

Traceable records for the completed works.

FireX prepared installation and inspection records using its BM TRADA Q-Mark recording process where applicable, together with the other project-specific records required for review and practical close-out.

  • Penetration location and reference
  • Dimensions of the penetration
  • Products and systems used
  • Specified fire-resistance rating
  • Before-and-after photographs
  • Additional installation and traceability information required by the project and FireX’s certified process

Programme outcome

Quantified delivery aligned with the wider programme.

Approximately 510 service penetrations were completed and 38 mechanical fire dampers installed across the basement through to the third floor during the five-month phased programme. Coordinating the works with the refurbishment sequence helped MG Construction release completed areas to follow-on trades while maintaining traceable records of the passive fire protection installed.

Explore FireX fire stopping

Talk to FireX

Planning a similar programme?

Share the building type, location, asset quantities, available survey information and target programme. We’ll review the requirement and set out the practical next step.