Public building case study
Complex passive fire remediation
Phased fire-stopping and compartmentation works within a live civic building, including congested service zones, controlled opening-up and evidence-led close-out.
Project requirement
The challenge.
Coordinate passive fire remediation across three live work areas where congested services and concealed construction required controlled investigation before a suitable repair could be confirmed.
Delivery control
How the work was managed.
Opening-up, fire-stopping and compartmentation work were phased around building use. Site conditions, interfaces and exceptions were recorded so that each location could be reviewed before concealment and close-out.
Evidence
Records prepared for practical close-out.
Safe sequencing around live building use, multiple trades and concealed fire compartment lines.
- Location and defect references
- Before, during and completion photographs
- Installed system and product information
- Exceptions requiring further technical resolution
Related capability
Services used on comparable requirements.
Every scope is confirmed against the building, available evidence and the limits of the relevant certification.
View public sector & local authorities capabilityConfidentiality
Why this case study is anonymised.
Client and location details are withheld where permission to publish has not been confirmed. The scale and delivery information above reflects FireX experience already presented publicly and does not imply endorsement by any organisation.
View all project experienceTalk to FireX
Planning a similar programme?
Share the building type, location, asset quantities, available survey information and target programme. We’ll review the requirement and set out the practical next step.